Minimum Version Required: 24.01
Pre-Conditions
Users should be familiar with Advanced Fusion Alert setups
Steps
When alerts are initially created, and there is a fusion report that fuels them, there will be a filter in the fusion report that references {LastStartTime}. You may notice that this {LastStartTime} is not pre-defined as a variable in the report.
The LastStartTime only takes effect when the Import Routine for the alert is under ImportProjectID=1126, 2044, 2043, 2046, or 2045. These are system Import Projects that are hardcoded to utilize this LastStartTime, and they technically reference the Last Run Time of the corresponding ImportRoutineSettings record.
If the ImportProject is changed, none of those system import projects can be placed back on the Import Routine. Instead, the options are to:
- Create a new Alert from scratch, or modify the LastStartTime filters of the report to use a pre-defined variable.
Best Practices
If a report is working, do not move the Import Routine to a different Import Project