Minimum Version Required: 22.01
Pre-Conditions
The Table Import will need to be based on a Report, Mailbox, or EDBL Client.
Steps
How to Schedule an Import
Import Routines are scheduled through an Import Project. An Import Project can hold multiple Import Routines. Use an existing Import Project and Schedule or create a new one.
1. Navigate to the Import Projects Table
2. Click Add Import Projects
3. Name the Import Project
4. Click Add Record
5. Navigate to you Import Routine and open the Table Import Wizard
6. Select the Import Scheduling tab
7. Select an ImportProject
8. Choose an existing schedule or click New Schedule
9. Enter values to all required and applicable optional fields displayed under the Settings form
10. Click Save Changes
Fields And Definitions
*Schedule Name - Descriptive name of the frequency, reason for import, etc.
*Frequency - How often the Import Routine will run (Daily, Weekly, Monthly)
Repeat Every Minutes - How many minutes the Import Routine will attempt to run within the set run times (For example: If set to 15 minutes and run time is 1 hour, the import routine will run 4 times)
Start Time - When the Import Routine will run for the first time
End Time - When the Import Routine will stop running (If the Repeat Every Minutes is longer than the duration between the Start and End Time, the Import Routine will only run once)
*Next Run Time - The date the Import Project/Routine will run
*Run Permission - The permission required to manually run the import outside of the schedule